Block #1:
- Parking construction works have been completed.
- Both elevators have been installed. Painting works in the elevator shafts are currently underway.
Block #2:
- Parking line marking works are nearing completion.
- Painting works in the elevator shafts are currently underway.
- Facade works have been completed.
- Roof waterproofing and screeding works have also been completed.
Block #3:
- Monolithic works are currently underway on the 4th floor.
- Framing of the perimeter walls has been completed from the -2 floor up to and including the 2nd floor.
- Blockwork construction is currently underway on the 2nd floor.
Block #4:
- The 21st-floor slab has been cast.
- Framing of the perimeter walls has been completed up to and including the 12th floor. Blockwork construction is currently underway on the same floor.
- Aluminum doors and windows have already been installed from the -3 floor up to and including the 6th floor.
Block #5:
- Construction of the slab for the 2nd residential floor (7th structural floor) is currently underway.
Block #6:
- Excavation works are nearing completion.